As a third-generation nuclear power plant design, construction of the Westinghouse AP1000 incorporates the characteristics of modular construction and the “Open-Top” lifting method, which results in many kinds of lifting operations, whose potential failure creates increased risk to key equipment and construction personnel. Lifting by its very nature is high risk. Based on traditional safety management practices utilized at the project, lift operation characteristics were analyzed, and procedures and processes developed to manage the risk. These developed aspects included: lifting operation procedures; a construction scheme review/approval process; work planning/risk mitigation; equipment inspections; personnel certification requirements; training; crew management; special inspections; lessons learned utilization; discipline management; emergency management; and safety culture development. The authors believe that the safety management approaches discussed in this paper can provide guidance in conducting safe lift operations in other nuclear power plant projects.
Skip Nav Destination
2013 21st International Conference on Nuclear Engineering
July 29–August 2, 2013
Chengdu, China
Conference Sponsors:
- Nuclear Engineering Division
ISBN:
978-0-7918-5582-9
PROCEEDINGS PAPER
Lifting Operation Safety Management in AP1000 Nuclear Plant Project
Xiaogang He,
Xiaogang He
State Nuclear Power Engineering Company, Sanmen, Zhejiang, China
Search for other works by this author on:
Shell Shortes
Shell Shortes
Chicago Bridge and Iron, Inc., Sanmen, Zhejiang, China
Search for other works by this author on:
Xiaogang He
State Nuclear Power Engineering Company, Sanmen, Zhejiang, China
Shell Shortes
Chicago Bridge and Iron, Inc., Sanmen, Zhejiang, China
Paper No:
ICONE21-16621, V005T12A014; 7 pages
Published Online:
February 7, 2014
Citation
He, X, & Shortes, S. "Lifting Operation Safety Management in AP1000 Nuclear Plant Project." Proceedings of the 2013 21st International Conference on Nuclear Engineering. Volume 5: Fuel Cycle, Radioactive Waste Management and Decommissioning; Reactor Physics and Transport Theory; Nuclear Education, Public Acceptance and Related Issues; Instrumentation and Controls; Fusion Engineering. Chengdu, China. July 29–August 2, 2013. V005T12A014. ASME. https://doi.org/10.1115/ICONE21-16621
Download citation file:
9
Views
Related Proceedings Papers
Related Articles
The Fabulous Nuclear Odyssey of Belgium
J. Pressure Vessel Technol (June,2009)
Plant Life Management Models: A Comparison With Analysis of Impact on Both Safety and Nonsafety Issues
J. Pressure Vessel Technol (June,2011)
Low-Power and Shut-Down Condition Medium-Break Loss-of-Coolant Accident Success Criterion Analysis for a Typical Three-Loop Nuclear Power Plant
ASME J of Nuclear Rad Sci (October,2016)
Related Chapters
Risk-Informed Licensing, Regulation, and Safety Management of NPPs in Finland
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 3, Third Edition
Czech and Slovakian Codes
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 3, Third Edition
Development of Nuclear Boiler and Pressure Vessels in Taiwan
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 3, Third Edition